REDEVELOPMENT REPORT
It’s been a beehive of activity over the last couple of weeks with everything moving along nicely. Our windows have started to go in so the cladding won’t be far away now. The electrical wiring is well on the way, the air conditioning ducting has been installed, the solar panels are on, the big limestone blocks are being laid out the front and the earthworks for the Lazarus Lounge have started.
The completion date is now early December so fingers crossed.
Images: The rear windows are in so the cladding should start this week. The roof under the roof on the left is going to have the AC and cool room compressors mounted on it so they’re out of the sun and will be partly hidden;
This is the retaining wall for the back of the Lazarus Lounge and behind that you can see the start of the roundabout;
These are Limestone blocks in front of the entry ramp;
The front windows are going in using Black Butt Eucalypt frames