22/06/2026
Hello Parkway,
Complete repair, restoration, redesign, reinforcement, and repainting of our North Lorraine Gate at Parkway Village...
Thank you to our contractor Marlon for a job well done...
Date of damage:
May 29,.2026
Date of complete repair:
June 22, 2026
21/06/2026
Flood Update at Parkway Village
As of today, 07:22pm
2026.06.21
For info and updates
Please call the PV guard house at 0917 185 2299
21/06/2026
Completion of cleanup and removal of plants growing from the sidewalk cracks...
Malinis na and walkable na po ang Caroline sidewalk...
Thank you Alex, Danny, Winnie and Lito...
Pending Works at Caroline Sidewalk
- cracked pavement sealing with concrete and other repair works
- sidewalk and gutter finishing and painting
- further beautification
Pending cleanup & clearing works in other areas at Parkway Village
- Lorraine Evangeline
- Katherine Antoinette
- Josephine Christine
- other areas
2026.06.21
21/06/2026
Happy Father's Day Parkway
"As a father shows compassion to his children, so the Lord shows compassion to those who fear him." - Psalm 103:13
🔨 🔧 🗜 🧰 👨 💪
20/06/2026
General Meeting of All PVHAI Employees with Administrative and HR Head at Parkway Village...
- work ethics and policies
- duty assignments
- grievances and mental health
- improvements in HOA services
- other matters
In coordination with Security and Maintenance Committee Heads, and PVHAI Pres Joey Mercado...
FYI: At present, the Association employs 8 security and 3 maintenance = total 11 personnel
At minimum wage of P658.00 per day x 11 personnel x 30 days, the salary expense to man the Association = P217,140.00 / month
This amount does not yet include government contributions, incentives and overtime...
Please continue to support the Association by paying your dues and back dues and by promoting the use of our paid facilities
2026.06.20
20/06/2026
Ongoing final painting of repaired and improved gate at North Lorraine at Parkway Village...
1 day na lang, tapos na...
Sa wakas...
Contractor: Marlon
2026.06.20
18/06/2026
Ongoing signage improvement at the PV store...
Instead of paint, it would be more practical to use tarpaulins for the PV Store signage / logo / advertisement...
Slotted angle bars shall be welded together to form a 30ft x 3.5ft metal frame that can support multiple 3ft tall tarps...
2 or 3 floodlights shall also be installed on the top most frame as to provide additional lighting to the Activity Center entrance at night...
Abangan ang before and after...
Contractor: Marlon
2026.06.18
18/06/2026
Ongoing checkup and roof leak repair at the PV Store...
- locating leaks and holes
- application of epoxy primer and vulcaseal mix
- final coat of roof guard paint
The PV Store is a rental property of the Association...
Contractor: Marlon
2026.06.17
18/06/2026
After nakawan ng metal gate, ginawa naman tambakan ng basura ang harapan ng isang private property at Christine, Parkway Village...
Nasaan ang malasakit niyo sa Parkway and sa atin kapaligiran?
Kung sakali matapos malinisan, mag tatambak uli kayo?
Or antay na lang tayo ng mataas na baha, para kusang babalik sa inyo ang tinapon niyo na basura?
2026.06.18
Near Christine Dulo, Barangay Apolonio Samson
16/06/2026
Application of red oxide metal primer at the North Lorraine Gate...
Solid na Solid...
Contractor: Marlon
2026.06.16