06/04/2026
Essentially our only issue comi by through the winter was #6. Here is what it looked back in late April. Now just into June it really has turned the corner. Surprising what a little heat will do 🙂 Jud & his crew worked hard to get it back but just needed a little time and help. We are lucky to have such an amazing crew at at the Club!
06/04/2026
And that’s a wrap!
Wow - what a difference those are going to make.
Our major cart path project finishes this afternoon right on schedule. 6 days on the course. Thanks to the membership for dealing with the chaos. The maintenance crew did a bunch of work to help out too. We are pretty lucky!! 😍🔥kudos to Kiminski Paving for a job well done.
06/03/2026
Day 5 photos! Let’s finish this thing off - 1 more day!! To say we’re excited is an under statement. Gully conquered ✅
Kiminski Paving
06/02/2026
Day 4 complete!
We are cruising now. 2/3 done. Holes 1-6 remain.
Tough not to be positive about this project - it’s good for riders, walkers and staff alike. Fire up!
06/01/2026
We are closing in on the clubhouse refresh. Multiple windows replaced, front entry revamp, and a new modern paint color to cover up our blemishes. A lipstick on a pig, but it’s pretty dang good lipstick. Thanks to the maintenance crew for handling all of this in-house!! It’s going to look great when it’s all said and done! You might not recognize the place when you first pull in. Maybe a new building will happen someday -until then. Cheers!
05/29/2026
#10 to finish off the week. About half done - back at it Monday!!
05/29/2026
Parking lot expansion plan is taking shape with most of the initial tree work completed. We are hoping to pick up 40-60 spots by the old tennis court to avoid having to park down the entry way for most events.
05/29/2026
Day 3 cart paths - close to finishing up the back 9!
Front 9 only again today. Weekend normal, all 18 holes open!!
05/27/2026
Day 2 cart path photos!
Lots of progress made. More work to be done!